Canberra

Image above: Ginninderry Regeneration Precinct, Canberra

Key trends

Summary: Canberra has entered a period of stronger market conditions and hence cost pressures. Escalation is forecast to average 4.0% p.a. for building and 5.1% p.a. for infrastructure from 2027 to 2029.

Competition for resources: Canberra will always compete with Sydney for key trades, so could see stronger cost pressures via Sydney’s data centre pipeline and, indirectly, by increased demand from Brisbane and south-east Queensland. However, the strength (set to be sustained for many years) in the nearby region’s renewables and transmission pipeline should also underpin strong demand for key trades closer to home.

Cost escalation
2026
2027
2028
2029
Escalation type
BAU
BAU
Total
Total
Building
4.1%
4.0%
4.0%
4.0%
Infrastructure
4.7%
4.5%
5.0%
5.7%

Local insights

• The Canberra market saw a period of softening conditions bottom out in 2025, when (building) escalation returned to the 3% baseline (the first market around Australia to see this since the pandemic). As this was happening, however, key drivers for construction were in the early stages of uplift. These were led by those for commercial construction, specifically the end of long lead times for the commencement of major new office buildings.

• The improved conditions seen in 2026, which seem set to continue into 2027, are largely expected in those sectors where federal funding is most important (e.g. office, entertainment and recreation, defence and transport infrastructure). The need to upgrade social and civil infrastructure reflecting years of robust population growth also played a role in seeing construction activity – and cost pressures – strengthen.

• Sectors linked to federal funding, as well as those typically driven by the private sector, are likely to continue to play a key role in the strength of overall market conditions, although likely federal and territory elections during 2028 may see an ‘air bubble’ in some projects due to any election-led uncertainty. In contrast, despite the strength of the proposed project pipeline, sectors and projects linked to territory funds may not come through as soon as expected (or hoped). While their capex funding remains robust and is set to deliver major projects in health, transport and entertainment in coming years, there is risk in the medium term, with the new Canberra stadium project unlikely until the 2030s.